go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_WPD_006
Title Sunshine Tariff
Status Completed
Energy Categories Renewable Energy Sources(Solar Energy, Photovoltaics) 50%;
Other Power and Storage Technologies(Electricity transmission and distribution) 50%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
Western Power Distribution
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 July 2015
End Date 01 February 2017
Duration 19 months
Total Grant Value £305,000
Industrial Sectors Power
Region South West
Programme Network Innovation Allowance
 
Investigators Principal Investigator Project Contact , Western Power Distribution (100.000%)
Web Site http://www.smarternetworks.org/project/NIA_WPD_006
Objectives

The project will address the following questions:

  1. Whether and how an offset connection agreement could be structured to be commercially viable for a generator?
  2. Whether and how an offset connection agreement could be structured and implemented to provide confidence to a DNO that the network will remain within operating limits?
  3. What mix of low tariff, behavioural signals and technology options would be most effective in shifting demand?
  4. What scale, longevity and reliability of demand side response would be achieved by the most effective method?

Expected Benefits:

  1. Understanding of feasibility of an offset connection agreement for both DNO and developer (including legal arrangements)
  2. Understanding of the capacity, longevity and reliability of domestic demand side response
  3. Recruitment of over 200 participants in the trial, on time and on budget
  4. Retention of at least 80% of participants through to the end of the trial
  5. Learning gained in the project successfully disseminated.
Abstract

Distribution Network Operators have an obligation to provide connections to customers in the most cost effective manner. However, due to the high penetration of distributed generation, several areas now require extensive reinforcement before additional generation can be connected. This can add significant time and costs to projects and can often make them unfeasible. Even with the introduction of alternative connections, where reinforcement costs are avoided on the acceptance of export constraint, the curtailment can be too severe for projects to be viable. As such there is continued interest in ways of connecting additional generation at minimal costs without compromising the security and quality of supply to existing customers. This project will investigate the feasibility of an "offset" connection agreement. With such an agreement, connection to a constrained network will be accepted with evidence that additional demand can be sourced to offset the generation. By incentivizing domestic demand shifting to times of peak PV output (10am-4pm, April to September), generation should be absorbed locally and have no effect on constraints at higher voltage levels. This project will trial a reduced "Sunshine Tariff" and determine the effect on demand profiles and its viability as the basis of a connection offer.Note : Project Documents may be available via the ENA Smarter Networks Portal using the Website link above

Publications (none)
Final Report (none)
Added to Database 14/12/18